Performance Record of Pulverizing Mill Installation Project

2012-2-27

NO.
Owner
Main project content
Date of beginning
Date of completion
Contract serial NO.
Remarks
1
Beng Bu Conch Cement Co., Ltd.
Annual capacity of six hundred thousand ton cement pulverizing mill mech. & elect. equipment installation
Oct., 2001.
50 days
2001-57
 
2
Nan Jing Conch Cement Co., Ltd.
Annual capacity of three hundred thousand ton cement pulverizing mill mech. & elect. equipment installation
Apr.17, 2002.
    60 days
2002-16
 
3
Wen Zhou Conch Cement Co., Ltd.
Annual capacity of one million six hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
May.25, 2002.
Sep.15, 2002.
2002-27
 
4
Shang Hai Conch Ming Zhu Cement Co., Ltd.
Annual capacity of sixhundred thousand ton cement pulverizing mill mech. & elect. equipment installation
June.20, 2002.
Sep.20, 2002.
2002-29
 
5
Chang Feng Conch Cement Co., Ltd.
Annual capacity of three hundred thousand ton cement pulverizing mill mech. & elect. equipment installation
Sep.25, 2002.
Nov.28, 2002
2002-37
 
6
Nan Jing Conch Cement Co., Ltd.
Annual capacity of one million ton cement pulverizing mill mech. & elect. equipment installation
2003 year
 
2003-36
 
7
Zhang Jia Gang Conch Cement Co., Ltd.
Annual capacity of one million six hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
2003 year
 
2003-37
 
8
Hai Men Conch Cement Co., Ltd.
Annual capacity of three million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
2004 year
 
2004-31
“φ4.2×14.5m ball mill ”installation technique wins the prize of “Erection Star” from China Installation Association
9
Jiang Men Conch Cement Co., Ltd.
Annual capacity of three million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Feb.17, 2005.
 
 
2005-07
 
10
Ying De Lung-shan Cement Co., Ltd.
Lung-shan 3PrdP line cement pulverizing mill mech. & elect. equipment installation project
2005 year
 
2005-06
 
11
Ying De Conch Cement Co., Ltd.
Ying De conch cements pulverizing mill mech. & elect. equipment installation project
Apr.2, 2005.
 
2005-12
 
12
Jiang Su Ba Ling Conch Cement Co., Ltd.
Annual capacity of three million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Apr.26, 2006.
 
2006-16
 
13
Chang Feng Conch Cement Co., Ltd.
Annual capacity of one million one hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Apr.26, 2006.
 
2006-15
 
14
Zhan Jiang Conch Cement Co., Ltd.
Annual capacity of three million two hundred thousand ton cement in Zhan Jiang Conch pulverizing mill mech. & elect. equipment installation project
Apr.10, 2007.
Aug.10, 2007.
2007-12
 
15
Ning Hai Qiang Jiao Conch Cement Co., Ltd.
Annual capacity of one million six hundred thousand ton cement in Ning Hai Qiang Jiao conch pulverizing mill mech. & elect. equipment installation project
Apr.10, 2007.
Aug.5, 2007.
2007-13
 
16
Shuang Feng Conch Cement Co., Ltd.
Annual capacity of one million six hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Oct.25, 2007.
208 days
2007-40
 
17
Chao Hu Hai Chang Cement Co., Ltd.
Annual capacity of two million four hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Mar.18, 2008.
 
2008-23
 
18
Anhui province Huai Ning Conch Cement Co., Ltd.
Annual capacity of six hundred thousand toncement pulverizing mill mech. & elect. equipment installation project
June, 2008.
3 months
2008-47
 
 
19
Ning Hai Qiang Jiao Conch Cement Co., Ltd.
Annual capacity of two million two hundred thousand ton cement in Qiang Jiao Conch the 2PndP phase pulverizing mill mech. & elect. equipment installation project
Dec.30, 2008.
 
2009-06
 
20
Guang Dong Qing Xin Cement Co., Ltd.
Annual capacity of four million four hundred thousand ton cements in Qing Xin Conch pulverizing mill mech. & elect. equipment installation project
2009 year
 
2009-23
 
21
 
Lin Xiang Conch Cement Co., Ltd.
Annual produce two million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Jul.23, 2009.
Mar.1, 2010.
2009-35
 
22
Gan Jiang Conch Cement Co., Ltd.
Annual produce two million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Jul.23, 2009.
Feb.1, 2010.
2009-36
 
23
Xiang Shan Conch Cement Co., Ltd.
Annual produce two million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Jul.23, 2009.
May.10, 2010.
2009-37
 
24
Chu Zhou Conch Cement Co., Ltd.
Annual produce two million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Dec.18, 2009.
 
2009-82
 
25
Huai Nan Conch Cement Co., Ltd.
Annual capacity of two million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Dec.18, 2009.
 
2009-83
 
26
Li Quan Conch Cement Co., Ltd.
1Pst Pphase annual capacity of four million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Jan.14, 2010.
 
2010-14
 
27
Guang Yuan Conch Cement Co., Ltd.
 
2PndP phase annual capacity of two million two hundred thousand ton cement pulverizing mill mech. & elect. equipment installation project
Aug.7, 2010.
Complete before middle of May, 2011
2010-67
 
28
Tai Wan (Chong Qing) Cement Corporation
Chong Qing(Ⅱ phase)clinker, grinding production line electromechanical equipment erection
2011.2.18
2011.9.26
2011-14
 
29
Long Ling Hui He Cement Corporation
Annually produce 1,100,000ton cement grinding electromechanical equipment erection
2011.5.18
2012.1.30
2011-30